Draft for expert review — unlisted page, not linked from the public site · feedback welcome: DM @finleyistan
buildmoredatacenters.com · feasibility assessment

Kootenai County, Idaho

PRIMARY UTILITY ANALYZED // Kootenai Electric Cooperative (member-owned co-op, BPA region, non-RTO)
SCENARIO // 25 MW primary · 100 MW scale-tested · RIGHT-SIZED MAX ON KEC // ~24 MW
PREPARED // July 25, 2026 · METHOD // public data + documented assumptions (shown in appendix)
County verdict: Conditional — bring-your-own-power

Kootenai County can host data centers, at the right sizes, on the right terms. The county's opportunity comes in two lanes: up to roughly 20–25 MW on Kootenai Electric Cooperative (headroom score 0.0/4 — every regional supply signal is tight), and mid-scale projects in Avista's service territory, which covers much of Coeur d'Alene and has roughly fifteen times KEC's system size. In both lanes the same condition applies, because both draw on the same constrained Pacific Northwest supply: the developer brings or funds its own generation and pays full marginal power costs. On that structure, the math is strongly positive for local ratepayers — a data center covering its own demand doesn't need to sell a single watt back to the grid; its fixed-cost payments simply spread the poles-and-wires costs that members currently carry alone. On a standard tariff, the same facility would raise bills. Structure decides everything.

1. The utilities serving this county

UtilityTypeScaleHeadroomRight-sized maxRequired structure
Kootenai Electric CooperativeCo-op33,486 meters · 588 GWh/yr · $61.6M revenue0.0/4 (RED)~24 MWBring-your-own-power + fixed-cost contribution; benefits flow to members automatically
Avista Corp.Investor-owned~420k electric customers regionwide (≈15× KEC)Not separately scored — same constrained BPA regionMid-scale possible w/ system studyBYO-power + a negotiated tariff mechanism; IOU margin does not flow to ratepayers automatically

The county is the unit of the verdict; the utility is the unit of the math. A rate impact can only be computed against a specific utility's sales, revenue, and tariff — there is no "county blended rate" to compute against. So this report scores each lane and then renders one county-level answer above. KEC is computed in full below because its cooperative structure makes it the cleanest demonstration of the mechanism (every dollar of margin returns to members automatically) and because its published cost data is unusually good. The Avista lane is assessed directionally — same regional supply constraint, same required structure — pending Avista-specific tariff and load data, which we would welcome.

1b. Why ~25 MW? The right-sizing logic

The 25 MW scenario is not arbitrary — it falls out of a sizing rule, stated here so it can be evaluated and challenged:

2. Grid headroom — the four signals

SignalFindingScore
Sales trendCounty population up >40% since 2010; member base growing steadily0.0
Resource adequacyBPA White Book projects regional energy deficits from 2027 (−370 MW) to −1,861 MW by 2030; E3 (Apr 2026) finds elevated shortage risk beginning 2026, especially winter; PNUCC 2026: resource development not keeping pace0.0
Power cost trendKEC's 2025 rate notice: BPA demand charges +24%, transmission +20%, attributed to scarcity; demand charges rising from 18% to ~25% of power costs within three years0.0
Rescuable retirementsRegion already short; new load worsens adequacy rather than preserving supply0.0

The decisive fact: KEC buys the majority of its power from BPA at cost — among the cheapest in the nation — but the allocation is capped. New large load is served at the expensive margin, not the blended rate members pay. A RED score with a viable generation pathway (KEC joined the 17-co-op PNGC Power consortium in 2024 to build new resources) maps to CONDITIONAL, not NOT-HERE.

3. Rate impact on members (25 MW)

StructureRate changeTypical household
A — standard tariff (gap between marginal cost and blended rate socialized)+4.2% to +14.8%+$61 to +$213/yr
B — bring-your-own-power (developer self-supplies; pays fixed-cost contribution)−7.1% to −14.2%−$102 to −$205/yr

The swing between rows is the entire decision — same facility, opposite outcomes, determined by tariff design.

Caveats stated plainly. (1) The fixed-cost share is unusually well sourced: KEC publishes that power supply is "42 to 45¢ of every dollar" members pay, implying ~56% fixed. (2) The marginal power cost (7.5¢/kWh, range 6–9.5¢) is an ASSUMPTION and drives Structure A — this is the number we'd most like KEC to correct. (3) The Structure B result exceeds the 3–6% band in published research because a 25 MW load is a third of this co-op's volume, outside anything those studies measured; realistically the contribution would split across rate reduction, capital credits, and reserves. Treat the low end as the planning number.

100 MW scale test: 745 GWh/yr = 127% of KEC's total current sales — cannot be analyzed as a KEC distribution customer. At that size the project belongs on Avista or dedicated generation.

4. Water

The county sits atop the Spokane Valley–Rathdrum Prairie Aquifer, an EPA sole source aquifer. Precedent matters: in 2002, cogeneration plants sought ~18M gallons/day and most of those rights were denied after public opposition.

Cooling design (25 MW)Gallons/dayLocal equivalent
Traditional evaporative~242,000~800 homes
Hybrid evaporative~47,000~160 homes
Closed-loop / air-cooled~2,700~9 homes

North Idaho's cool, dry climate supports closed-loop and air cooling with minimal efficiency penalty — a genuine siting advantage. Recommendation: closed-loop or air cooling as a non-negotiable permit condition with annual public reporting.

5. Jobs and taxes (25 MW)

6. What a good deal looks like here

  1. Adopt a large-load tariff before entertaining any proposal — negotiating after a developer is at the table is the weakest position.
  2. Full marginal power-cost pass-through; the members' capped federal hydro is never blended into the data center's rate.
  3. Developer-funded generation contracted through PNGC Power, so the scale benefits all member co-ops.
  4. Closed-loop or air cooling in the permit, with annual public water reporting.
  5. Fixed-cost contribution above proportional share via demand and facilities charges — the specific mechanism that lowers member rates.
  6. Take-or-pay minimums, exit fees, and collateral; a 25 MW departure without protection strands costs on 33,000 members.
  7. A deliberate commissioners' decision on the property-tax exemption — granting it fully largely erases the fiscal case during the construction-impact years.

7. What would change the answer

Appendix — key inputs and arithmetic

InputValueBasis
KEC annual retail sales (S)587,998 MWhEIA-derived utility profile
KEC annual revenue (R)$61.56MEIA-derived utility profile
Blended rate10.47¢/kWh (residential 12.68¢)computed / profile
Fixed-cost share (F)0.56KEC: power supply = 42–45¢ of every $1
Marginal supply cost7.5¢/kWh (6–9.5¢)ASSUMPTION — please correct
Fixed-cost contribution factor (k)0.6 (0.4–0.8)ASSUMPTION
County FY2026 budget$144Mcounty commission, Aug 2025

E_dc(25MW) = 25 × 8,760 × 0.85 = 186.2 GWh = 31.7% of S · right-size cap (30% of S) → ~24 MW
Structure A: (0.075 − 0.0461) × 186.2M ÷ 588M = +0.92¢/kWh = +8.8% (mid)
Structure B: c_f = 0.56 × 0.1047 × 0.6 = 3.52¢ → $6.55M/yr → −1.11¢/kWh = −10.6% (mid)

Principal sources: Kootenai Electric Cooperative published rate materials and news releases (kec.com) · EIA-derived KEC utility profile · BPA Pacific Northwest Loads & Resources Study · E3 Greater Northwest Resource Adequacy assessment (Apr 2026) · PNUCC 2026 Regional Forecast · Kootenai County budget records and assessor materials (kcgov.us) · Idaho Commerce data center exemption terms · EPA/Idaho DEQ sole source aquifer designation · BoiseDev and Idaho Conservation League legislative coverage (2025–26).

This assessment uses public data and documented assumptions to estimate outcomes. It is not a substitute for a utility system impact study, a formal fiscal impact analysis, or legal and engineering review. Verify figures with the serving utility and county assessor before citing them publicly. Where a figure could not be sourced, it is marked as an assumption rather than presented as fact. Prepared by buildmoredatacenters.com — corrections actively solicited, especially from Kootenai Electric Cooperative.