Kootenai County can host data centers, at the right sizes, on the right terms. The county's opportunity comes in two lanes: up to roughly 20–25 MW on Kootenai Electric Cooperative (headroom score 0.0/4 — every regional supply signal is tight), and mid-scale projects in Avista's service territory, which covers much of Coeur d'Alene and has roughly fifteen times KEC's system size. In both lanes the same condition applies, because both draw on the same constrained Pacific Northwest supply: the developer brings or funds its own generation and pays full marginal power costs. On that structure, the math is strongly positive for local ratepayers — a data center covering its own demand doesn't need to sell a single watt back to the grid; its fixed-cost payments simply spread the poles-and-wires costs that members currently carry alone. On a standard tariff, the same facility would raise bills. Structure decides everything.
| Utility | Type | Scale | Headroom | Right-sized max | Required structure |
|---|---|---|---|---|---|
| Kootenai Electric Cooperative | Co-op | 33,486 meters · 588 GWh/yr · $61.6M revenue | 0.0/4 (RED) | ~24 MW | Bring-your-own-power + fixed-cost contribution; benefits flow to members automatically |
| Avista Corp. | Investor-owned | ~420k electric customers regionwide (≈15× KEC) | Not separately scored — same constrained BPA region | Mid-scale possible w/ system study | BYO-power + a negotiated tariff mechanism; IOU margin does not flow to ratepayers automatically |
The county is the unit of the verdict; the utility is the unit of the math. A rate impact can only be computed against a specific utility's sales, revenue, and tariff — there is no "county blended rate" to compute against. So this report scores each lane and then renders one county-level answer above. KEC is computed in full below because its cooperative structure makes it the cleanest demonstration of the mechanism (every dollar of margin returns to members automatically) and because its published cost data is unusually good. The Avista lane is assessed directionally — same regional supply constraint, same required structure — pending Avista-specific tariff and load data, which we would welcome.
The 25 MW scenario is not arbitrary — it falls out of a sizing rule, stated here so it can be evaluated and challenged:
| Signal | Finding | Score |
|---|---|---|
| Sales trend | County population up >40% since 2010; member base growing steadily | 0.0 |
| Resource adequacy | BPA White Book projects regional energy deficits from 2027 (−370 MW) to −1,861 MW by 2030; E3 (Apr 2026) finds elevated shortage risk beginning 2026, especially winter; PNUCC 2026: resource development not keeping pace | 0.0 |
| Power cost trend | KEC's 2025 rate notice: BPA demand charges +24%, transmission +20%, attributed to scarcity; demand charges rising from 18% to ~25% of power costs within three years | 0.0 |
| Rescuable retirements | Region already short; new load worsens adequacy rather than preserving supply | 0.0 |
The decisive fact: KEC buys the majority of its power from BPA at cost — among the cheapest in the nation — but the allocation is capped. New large load is served at the expensive margin, not the blended rate members pay. A RED score with a viable generation pathway (KEC joined the 17-co-op PNGC Power consortium in 2024 to build new resources) maps to CONDITIONAL, not NOT-HERE.
| Structure | Rate change | Typical household |
|---|---|---|
| A — standard tariff (gap between marginal cost and blended rate socialized) | +4.2% to +14.8% | +$61 to +$213/yr |
| B — bring-your-own-power (developer self-supplies; pays fixed-cost contribution) | −7.1% to −14.2% | −$102 to −$205/yr |
The swing between rows is the entire decision — same facility, opposite outcomes, determined by tariff design.
Caveats stated plainly. (1) The fixed-cost share is unusually well sourced: KEC publishes that power supply is "42 to 45¢ of every dollar" members pay, implying ~56% fixed. (2) The marginal power cost (7.5¢/kWh, range 6–9.5¢) is an ASSUMPTION and drives Structure A — this is the number we'd most like KEC to correct. (3) The Structure B result exceeds the 3–6% band in published research because a 25 MW load is a third of this co-op's volume, outside anything those studies measured; realistically the contribution would split across rate reduction, capital credits, and reserves. Treat the low end as the planning number.
100 MW scale test: 745 GWh/yr = 127% of KEC's total current sales — cannot be analyzed as a KEC distribution customer. At that size the project belongs on Avista or dedicated generation.
The county sits atop the Spokane Valley–Rathdrum Prairie Aquifer, an EPA sole source aquifer. Precedent matters: in 2002, cogeneration plants sought ~18M gallons/day and most of those rights were denied after public opposition.
| Cooling design (25 MW) | Gallons/day | Local equivalent |
|---|---|---|
| Traditional evaporative | ~242,000 | ~800 homes |
| Hybrid evaporative | ~47,000 | ~160 homes |
| Closed-loop / air-cooled | ~2,700 | ~9 homes |
North Idaho's cool, dry climate supports closed-loop and air cooling with minimal efficiency penalty — a genuine siting advantage. Recommendation: closed-loop or air cooling as a non-negotiable permit condition with annual public reporting.
| Input | Value | Basis |
|---|---|---|
| KEC annual retail sales (S) | 587,998 MWh | EIA-derived utility profile |
| KEC annual revenue (R) | $61.56M | EIA-derived utility profile |
| Blended rate | 10.47¢/kWh (residential 12.68¢) | computed / profile |
| Fixed-cost share (F) | 0.56 | KEC: power supply = 42–45¢ of every $1 |
| Marginal supply cost | 7.5¢/kWh (6–9.5¢) | ASSUMPTION — please correct |
| Fixed-cost contribution factor (k) | 0.6 (0.4–0.8) | ASSUMPTION |
| County FY2026 budget | $144M | county commission, Aug 2025 |
E_dc(25MW) = 25 × 8,760 × 0.85 = 186.2 GWh = 31.7% of S · right-size cap (30% of S) → ~24 MW
Structure A: (0.075 − 0.0461) × 186.2M ÷ 588M = +0.92¢/kWh = +8.8% (mid)
Structure B: c_f = 0.56 × 0.1047 × 0.6 = 3.52¢ → $6.55M/yr → −1.11¢/kWh = −10.6% (mid)
Principal sources: Kootenai Electric Cooperative published rate materials and news releases (kec.com) · EIA-derived KEC utility profile · BPA Pacific Northwest Loads & Resources Study · E3 Greater Northwest Resource Adequacy assessment (Apr 2026) · PNUCC 2026 Regional Forecast · Kootenai County budget records and assessor materials (kcgov.us) · Idaho Commerce data center exemption terms · EPA/Idaho DEQ sole source aquifer designation · BoiseDev and Idaho Conservation League legislative coverage (2025–26).